The Arbor Hills Neighborhood Association is located in Madison, Wisconsin. The neighborhood association was organized in August 1967. Email Arbor Hills Neighborhood Newsletter requests to newsletter@arborhills.org UPDATES/NEWS: (Updated JUNE 24, 2007) NOTICE: On Monday night June 25th between the hours of 11 PM and 6AM, the Verona Road (USH 151) exit ramp from the WB Beltline will be closed so that the Contractors can mill and pave the ramp area. On Tuesday night June 26th between the hours of 11 PM and 6AM, the Verona Road (USH 151) on ramp to the EB Beltline will be closed so that the Contractors can mill and pave the ramp area. Message boards will be utilized to detour traffic from these ramps. The detour route will utilize the Whitney Way interchange.
Planned construction operations for week starting Sunday, June 24th. The following is a listing of work that is proposed for the week:
1) Milling and Asphalt paving operations will continue next week (Monday - Thursday nights - 9PM to 6AM) throughout the project limits. 2) Todd Drive Bridge - Stage 2 deck was poured on 6/21/07. The contractor will be working on completing the bridge work over the next 2 weeks. 3) Sawing and Concrete base patching work was completed on 6/22/07 early AM. 4) Ramp closures that are planned for next week
5) Barrier wall replacement by the Todd Drive Bridge will take place Thursday June 28th and Friday June 29th during the day. No closures required for this work.
Several other general notes that will take place with the Project:
Posted June 17, 2007 NOTICE: On Saturday morning June 16th, the EB Beltline lanes will be closed to 1 lane between the Verona Road Bridge and Seminole Highway. The lane closure will be removed at approximately 10:00 AM Saturday morning. This is a slight change from normal procedure (open by 6 AM). The closure is required to facilitate completion of concrete base patching in the EB lanes by the Verona Road/USH 151 on-ramp to EB Beltline.
Planned construction operations for week starting Sunday, June 17th. The following is a listing of work that is proposed for the week:
1) Milling operations will start next week (Thursday night - 9PM to 6AM). This will continue into the weekend and into the following week. 2) Bridge decking work will continue throughout the week and the stage 2 decks will be poured late in the week. 3) Sawing and Concrete base patching work will conclude late in the week (NIGHTS ONLY). 4) A Seminole Hwy exit Ramp closure is tentatively scheduled for Thursday night June 21st. 5) Barrier wall replacement will take place sometime during the week (Tuesday or Wednesday) by the old Railroad track area.
Several other general notes that will take place with the Project:
Posted June 10, 2007 Planned construction operations for week starting Sunday, June 10th. The following is a listing of work that is proposed for the week:
1) Traffic was switched to the outside lanes of the EB & WB Beltline over the last 2 nights. The next phase of the project will be approximately 31 days or until about July 8th.
2) Bridge demolition work will continue thru the weekend (June 9th and June 10th) and thru next week.
3) Sawing and Concrete base patching work will continue starting Friday night June 8th from 9PM to 6AM. It is anticipated that this work will continue throughout the next several weeks (NIGHTS ONLY).
4) No Ramp closures are currently scheduled for this upcoming week.
5) Barrier wall removal will continue throughout the week by the Todd Drive Bridge and by the old Railroad track area.
Several other general notes that will take place with the Project:
Posted June 3, 2007 Planned construction operations for week starting Sunday, June 3rd. The following is a listing of work that is proposed for the week: 1) The contractor will be finishing the 1st stage of the Todd Drive Bridge early in the week. Phase 2 bridge demolition will start late in the week. 2) Traffic will be switched to the 2 outside lanes of the Beltline during the week. The schedule (9PM 6AM) is to switch the EB Beltline lanes on either Wednesday night or Thursday night (June 6th or June 7th). The WB Beltline lanes will be switched on either Thursday night or Friday night (June 7th or June 8th). The lanes will be switched on 2 consecutive nights during the week, but at this time I cant predict which sets of nights this will happen. Weather will play a large role on which nights the work can take place. The Beltline will remain in 2 lanes in each direction during this next phase of the project (build the inside lanes and inside half of the Todd Drive Bridge). It is anticipated that the next phase will take approximately 31 days to do the work. The final phase of the project is to pave the final lift of asphalt on the entire Beltline (at night). 3) Ramp closures that are currently scheduled for this upcoming week are as follows: The ramps will be closed from 9PM to 6AM on the listed dates unless otherwise noted: Ramp closures are needed to facilitate the work in a safe manner for the contractors and the traveling public. Wednesday or Thursday night EB Beltline on-ramp from Seminole Hwy Wednesday or Thursday night EB Beltline exit-ramp to Todd Drive Wednesday or Thursday night EB Beltline on-ramp from Todd Drive Wednesday or Thursday night EB Beltline exit-ramp to SB Fish Hatchery Road Wednesday or Thursday night EB Beltline on-ramp from SB Fish Hatchery Road Wednesday or Thursday night EB Beltline exit-ramp to NB Fish Hatchery Road Wednesday night WB Beltline on-ramp from NB Fish Hatchery Road (9PM to 1AM) Wednesday night WB Beltline on-ramp from SB Fish Hatchery Road (9PM to 1AM) Thursday or Friday night WB Beltline on-ramp from NB Fish Hatchery Road Thursday or Friday night WB Beltline on-ramp from SB Fish Hatchery Road Thursday or Friday night WB Beltline exit-ramp to Todd Drive Thursday or Friday night WB Beltline on-ramp to Todd Drive
Several other general notes that will take place with the Project:
Posted May 28, 2007 Planned construction operations for week starting Sunday, May 27th. The following is a listing of work that is proposed for the week:
1) The contractor will be finishing the 1st stage of the Todd Drive Bridge throughout the week.
2) On Tuesday night, May 28th thru Friday night June 1st, concrete base patching work will continue in the EB & WB lanes from 9PM to 6AM. The Beltline will be closed to 1 lane in each direction (weather permitting) from Verona Road to Fish Hatchery Road.
3) Ramp closures that are currently scheduled for this upcoming week are as follows: The ramps will be closed from 9PM to 6AM on the listed dates unless otherwise noted: Please note that next week will be very busy at night with milling and paving operations taking place. Due to the nature of the milling and paving work, numerous ramp closures are needed to facilitate the work in a safe manner for the contractors and the traveling public.
Tuesday May 29th EB Beltline on-ramp from Todd Drive Tuesday May 29th EB Beltline exit-ramp to SB Fish Hatchery Road Tuesday May 29th EB Beltline on-ramp from SB Fish Hatchery Road Tuesday May 29th EB Beltline exit-ramp to NB Fish Hatchery Road Tuesday May 29th WB Beltline exit-ramp to Todd Drive Tuesday May 29th WB Beltline exit-ramp to Seminole Hwy
Wednesday May 30th EB Beltline on-ramp from Seminole Hwy Wednesday May 30th EB Beltline exit-ramp to Todd Drive Wednesday May 30th EB Beltline on-ramp from Todd Drive Wednesday May 30th WB Beltline on-ramp from NB Fish Hatchery Road (9PM 1AM) Wednesday May 30th WB Beltline on-ramp from SB Fish Hatchery Road (9PM 1AM) Wednesday May 30th WB Beltline exit-ramp to Todd Drive Wednesday May 30th WB Beltline on-ramp to Todd Drive Wednesday May 30th WB Beltline exit-ramp to Seminole Hwy Thursday (AM) May 31st EB Beltline exit-ramp to SB Fish Hatchery Road (1AM - 6AM) Thursday (AM) May 31st EB Beltline on-ramp from SB Fish Hatchery Road (1AM 6AM) Thursday (AM) May 31st EB Beltline exit-ramp to NB Fish Hatchery Road (1AM 6AM)
Thursday (PM) May 31st WB Beltline on-ramp from NB Fish Hatchery Road Thursday (PM) May 31st WB Beltline on-ramp from SB Fish Hatchery Road Thursday (PM) May 31st WB Beltline exit-ramp to Todd Drive Thursday (PM) May 31st WB Beltline on-ramp from Todd Drive Thursday (PM) May 31st WB Beltline exit-ramp to Seminole Hwy
Ramp closures updates for Friday will be posted next week on Wednesday May 30th.
Please note: The new Todd Drive off ramp from WB Beltline is scheduled to be paved on Tuesday night May 29th. The new ramp may be open on Wednesday May 30th weather permitting.
Several other general notes that will take place with the Project:
Posted May 23, 2007 Update for ramp closures (9PM to 6AM) for the rest of the week.
Posted May 18, 2007 Planned construction operations for week starting Sunday, May 20th. The following is a listing of work that is proposed for the week:
1) The contractor will be pouring the 1st stage of the Todd Drive Bridge decks on Tuesday and Wednesday mornings. The bridge work is on schedule.
2) On Monday night, May 21th thru Thursday night May 24th, concrete base patching work will continue in the EB & WB lanes from 9PM to 6AM. The Beltline will be closed to 1 lane in each direction (weather permitting) from Verona Road to Fish Hatchery Road.
3) Ramp closures that are currently scheduled for this upcoming week are as follows: The ramps will be closed from 9PM to 6AM on the listed dates.
§ Monday night, May 21st . Todd Drive exit ramp from WB Beltline § Tuesday night, May 22nd. Todd Drive on ramp to WB Beltline § Wednesday night, May 23rd . Seminole Hwy exit ramp from WB Beltline § Thursday night, May 24th. Seminole Hwy exit ramp from WB Beltline § Further updates will follow early next week.
4) Milling and paving operations will start Wednesday night May 23rd in the EB Beltline lanes from Seminole Hwy to Fish Hatchery Road.
Please note: The new Todd Drive off ramp from WB Beltline is scheduled to be paved on Thursday night May 24th. The new ramp may be open on Friday May 25th. Further updates will be given on the opening of the ramp.
Several other general notes that will take place with the Project:
Posted May 13, 2007 Planned construction operations for week starting Sunday, May 13th. The following is a listing of work that is proposed for the week: 1) On Saturday morning, May 12th, the Todd Drive on-ramp to EB Beltline will open. This meets the 7 day completion requirement for this ramp. 2) The Todd Drive Bridge construction including demolition of the existing bridge deck will continue day and night throughout the week. After demolition is complete early in the week, the crews will prepare for the new deck surface. 3) On Monday night, May 14th thru Friday night May 18th, concrete base patching work will continue in the EB & WB lanes from 9PM to 6AM. The Beltline will be closed to 1 lane in each direction (weather permitting) from Verona Road to Fish Hatchery Road. 4) Ramp closures that are currently scheduled for this upcoming week are as follows: The ramps will be closed from 9PM to 6AM on the listed dates.
§ Monday night, May 14th. Todd Drive exit ramp from EB Beltline § Tuesday night, May 15th. South Fish Hatchery Road exit ramp from EB Beltline § Tuesday night, May 15th. South Fish Hatchery Road on ramp to EB Beltline § Wednesday night, May 16th. North Fish Hatchery Road on-ramp to WB Beltline § Thursday night, May 16th. North Fish Hatchery Road on-ramp to WB Beltline
§ Tuesday night, May 15th, Todd Drive under the bridge may have to be closed for short durations to work on several bridge items. I can update this issue further early next week.
Several other general notes that will take place with the Project:
Posted May 6, 2007
Ramp closures that are planned for this week over the next couple of days 5/9/07.
The ramp closures are for concrete base patching in the EB lanes that are adjacent to the ramps listed above.
Posted May 6, 2007 Planned construction operations for week starting Sunday, May 6th. The following is a listing of work that is proposed for the week: On Friday night, May 4th, the WB Beltline lanes will be shifted towards the median from just east of Seminole Highway to Fish Hatchery Road. The NB Fish Hatchery Road on ramp to WB Beltline will be closed during the night-time hours to allow the pavement marking removal and new paint lines to be completed. After Friday night, the WB Beltline will be down to 2 lanes at 11 wide. On Saturday morning, May 5th, temporary concrete barrier wall will be installed in the EB & WB directions in a 700 long stretch over the Todd Drive Bridge. This work will be done during the day. No additional lane closures are needed for this work.
Several other general notes that will take place with the Project:
Posted April 29, 2007 Construction operations will begin on Monday April 30th. The following is a listing of work that is proposed for the week:
Several other notes that will take place with the Project that are too numerous to single out:
The schedule I listed above is what the Contractors anticipate. Weather may play a role in the schedule being altered. If you have any questions, please give me an email and I will respond.
|
|